Project Management Tools: Work Plans, Action Logs, or Both?

June 13, 2018 by Elizabeth HarrinElizabeth Harrin



“Dear Elizabeth: I use very simple tools to manage my projects. My projects are small scale, and I generally just verbally update my client or send a weekly progress note. I have a work plan, which is a list of activity areas with sub-tasks down one column and dates across the top. This is what I use to record the actions required to deliver the project. I also have an actions log, which I use to note down those actions that crop up in client meetings or emails.

I’m finding I use one or other, but not both. For example, on my current project, I primarily use the work plan. On my previous project, I used the actions log. I like to get my tools in place early so that everything is set up once the project goes live. I’m worried I might not be recording actions and progress sufficiently accurately. Should I be using a work plan and an actions list, both together?”

Thanks for such a great question! I get a sense of the kind of things you are doing and how you are managing your work. I think many project managers struggle with knowing what the “right” tools are for the job, especially when they’ve had very little training or support from their organization. It’s very common for there to be multiple ways of recording actions and project tasks within a business, because each project manager has found solutions that fit their style.

The first thing I want to say is that you probably shouldn’t be worried. The fact that you say you are worried about recording your progress and actions with sufficient accuracy means that you are most likely doing enough. We tend to worry about things and then overcompensate.

Related: Measuring the Success (or Failure) of Projects

If your clients are happy, your projects are getting done on time and you’re not overspending, then you are doing a good job!

What this is all about, then, is whether you could be more efficient, more confident, and feel more organized if you had the tools to support you in your work.

You’re using two organization tools: a work plan (which in project management speak we would call a project schedule) and an action log.

First, let’s look at the project schedule. This is your list of activities and dates. From how you have described it, it sounds like you’ve created a visual chart of tasks and the time they take, or the key milestones, in a spreadsheet. I’ve done this in the past too. It’s a simple way of keeping on top of the plan for the project, and the dates make it easier to see what has to be done by when.

What you have created is a Gantt chart. The biggest problem I have found with spreadsheet-based Gantt charts is that they take an age to update manually. I currently have a very simple one that is tracking activities for a particularly busy 3 week period on my project, for a large group of people who have no experience with enterprise project management solutions. It works fine, but it’s a headache to have to change the color of the cells every time someone says that a task is going live on a different day.

Related: 4 Ways LiquidPlanner Gantt Charts Are Smarter

It is much easier to create and edit Gantt charts in “proper” scheduling software. It might not feel like that when you first start using them, but once you’re out the other side of the learning curve, you can whip up and edit a project schedule in minutes (and replicate a new schedule from an old one, if you are doing similar projects over and over again).

The challenge then is sharing the information with your stakeholders, if they don’t use the same tools and don’t have the experience of being able to read and interpret a Gantt chart. That doesn’t sound like it would be an issue for you if you are updating your clients verbally or with a short progress report on email.

You’re also using an action log. Project managers around the world do the same thing!

Action logs are great for noting down tasks that come from meetings, conversations and emails. They aren’t tasks you would put on your project schedule, but they are things that need to be done. I have one on my projects too, and it’s full of things like ‘Check Fred has done the software load for the month’ (action for me), and ‘Send slides from last week’s board meeting to Sam’ (action for someone else).

I’d never put these activities into a Gantt chart. They aren’t the appropriate level of detail. Having said that, we need to record them somewhere. A project manager’s job is all about detail and making sure nothing falls through the cracks. You can only do this if you have a way of recording what needs to happen, because you can’t hold all those tasks in...

(RSS generated with FetchRss)

Previous Article
Create More Powerful and Robust Reports with LiquidPlanner
Create More Powerful and Robust Reports with LiquidPlanner

A living, breathing LiquidPlanner workspace is a gold mine of data about your team.Looking towards the futu...

Next Article
3 Steps to Bringing Order and Teamwork to Your Next Project