Ask a Project Manager: My Client Missed Their Deadline…Again!

January 23, 2018 by Elizabeth HarrinElizabeth Harrin

“Dear Elizabeth,

I work for a smallish web development company. We do our best to hit deadlines, but often when we fall behind it’s because of the client’s failure to do their part of the project on time. In particular, it’s getting access to creative materials like their brand fonts, or access to data or content that we require to move forward.

It’s also around decisions and approvals. They don’t seem to realize that if they take longer than planned to let us know their final position, we can’t continue with the project. What tips do you have for solving this problem?”  

This situation is more common than you might think, especially where the client is not used to working with project managers or services firms like your own. I’ve certainly been in situations where the customer’s own delay has had an impact on our ability to complete the work, so I understand where you are coming from and the frustration it can cause to your team.

Here are some suggestions to help.

You probably have a kick off meeting already for each project (if not, start doing that as a matter of course). Use the time in the meeting to set expectations about deliverables on both sides. Take the opportunity to get ultimate clarity on what it is you need them to do. Agree turnaround times for decisions.

With these assumptions set, you will hopefully have a better chance of them following through.

Document the meeting, the assumptions, the roles and responsibilities and share this paperwork with the client for signature. You could even make it part of your statement of work or project brief.

[Further Reading: How to Build Good Relationships with Project Stakeholders]

If it isn’t too late, consider adding relevant clauses to your contracts that relate to how you deal with late deliverables from clients and what the escalation route should be within the client organization should this happen.

If this is a regular occurrence, you can build in contingency to your plans. Ask for assets like brand fonts and logos as soon as the ink is dry on the contract. Get moving on the elements that you know normally cause an issue for you on projects.

You won’t be able to do this on things like decisions, but some things can be delivered early, even if you then don’t need to use them for several weeks.

However, let’s be realistic. Sometimes the people at that meeting commit to things that they then aren’t responsible for following through on. They might be the wrong people to make those commitments. Or life might get in the way and when the time comes they still fail to do what is required of them.

If your client fails to follow through on their side of the bargain, remind them of what they signed up for and gently explain why it’s important that deadlines are hit.

This might work, especially if it’s coupled with project reporting that points out you are waiting on the client for the next deliverable, or input to the next deliverable.

Be clear and specific in project reporting, stating what will happen if deliverables or decisions are not forthcoming. Some consequences of late client impact would be:

In my experience, loss of resources is the main one that gets clients to speed up. If they know they are going to lose a key resource, who knows the project and their business, and have to start working with someone else from scratch in a few weeks when they have finally made the decision, then they tend to speed up.

Keep talking to them, especially as deadlines approach. You can put weekly calls in place during critical times of the project. This gives you a regular touch point to remind them of their upcoming decision points and gives them time to get organized.

[Further Reading: 6 Ways to Improve Client Relationships]

At really important times in the project, you can move to daily calls. Anything that keeps reminding them that there is a decision due and that the work is waiting on them before being able to move forward. Document your calls, even if it’s a quick email afterwards to the people in the discussion. That way, everyone has a record of next steps and outstanding actions. Then refer to that list at the start of the next call. Sometimes the continual chasing is all that’s required.

Sometimes the delay isn’t due to the person you are in contact with daily. It might be that they can’t get time with their manager or the decision maker. Listen out for where you think you are speaking to the wrong person in the hierarchy so that you can redirect communication to the right...

(RSS generated with FetchRss)

Previous Article
5 Ways to Lead a Change Management Initiative: Project Manager As Change Manager
5 Ways to Lead a Change Management Initiative: Project Manager As Change Manager

Just over 325 years ago, Sir Isaac Newton explained to the world why planets orbit the way they do, while r...

Next Article
How to Pitch a New Idea to Your Boss in 5 Steps
How to Pitch a New Idea to Your Boss in 5 Steps

You have a great idea. You’re ready to implement it. But first, you need to get your boss’s approval. Here ...